Excerpt from October 10, 2024 Township Email Newsletter:

New Community Room:

   

Current Work Status: Community Room:

Concrete is all poured. Front columns are installed. Mudding of drywall continues. Dumpster enclosure is taking shape.

Excerpt from September 30, 2024 Township Email Newsletter:

New Community Room:
  
Current Work StatusCommunity Room:
Windows are installed. The dry wall is complete and the taping has begun.     

 

 

Excerpt from September 9, 2024 Township Email Newsletter:

New Community Room:

  

Current Work StatusCommunity Room:
The framing, retaining wall, storm piping, & parking lot base are all finished. This week the insulation will be inspected, drywalling begins, and we await the delivery of windows and doors.  

 

 

Excerpt from August 9, 2024 Township Email Newsletter:

Update on the New
Community Building Construction:


The Community Building, located south of the Township Administration Building at 8501 Kinsman Road, will have an Event Hall of approximately 1,700 square feet.

The Event Hall will be available to reserve for rental, and it will be an open space intended to accommodate different types of events.

Wi-fi will be available along with multiple large monitors/screens for audio/video presentations or displays.

One wall will have a countertop and sink available.

Two individual restroom facilities will be near the main entrance.

A paved terrace will be to the west of the building. 

Current Community Building status:
The framing is well underway.

The asphalt shingle roof is on.

We are waiting for windows and doors to arrive.

The sneak peek of the interior roofline photos look quite attractive!

The township trustees have named the new facility...
The Russell Township Community Room. 

 

 

Excerpt from July 3, 2024 Township Email Newsletter:

Update on the New
Community Building Construction:


The Community Building, located south of the Township Administration Building at 8501 Kinsman Road, will have an Event Hall of approximately 1,700 square feet. The Event Hall will be available to reserve for rental, and it will be an open space intended to accommodate different types of events. Wi-fi will be available along with multiple large monitors/screens for audio/video presentations or displays. One wall will have a countertop and sink available. Two individual restroom facilities will be near the main entrance. A paved terrace will be to the west of the building. 

Current Community Building status: The concrete floor went in a couple of weeks ago and the framers started this week. What a difference walls make! The trustees are purchasing furniture and considering a name for the new facility.

 

 

Excerpt from May 7, 2024 Township Email Newsletter:

Sneak Peek of the
Community Meeting Building:


The Community Meeting Building will have an Event Hall of approximately 1,700 square feet. The Event Hall will be available to reserve for rental, and it will be an open space intended to accommodate different types of events. Wi-fi will be available along with multiple large monitors/screens for audio/video presentations or displays. One wall will have a countertop and sink available. Two individual restroom facilities will be near the main entrance. A paved terrace will be to the west of the building. 

Current status: When the rain stops it will be time to prepare for and pour the concrete slab. 

Always feel welcome to contact us with your comments and questions. You may reply to this email or use contact info available on the pages of the township website.  

 

 

Link to Feb 21, 2024 Township Email Newsletter:

https://mailchi.mp/d1ec69132c81/russell-township-newsletter-10520662